ROAD CONSTRUCTION
The Township will be constructing a new Salt Storage Shed and Storage Building in the spring of 2023. A portion of Ridge Meadow Road will be closed during construction. A detour on to Five Forks Road will be in place off of Rt. 851 (Bridgeview Road). These projects are being funded through ARPA relief funds the Township received in 2021 & 2022.
2023 PROPOSED ROAD PROJECTS
- Leib School Road- 25mm – 4,111 ft. – 12,5000 Tons – $120,000 (Anderson Road to Route 851)
- Fox Run Court – Level coat – Estimated 150 Tons- $12,500
- Fox Run Court- 12.5 mm- 1,200 ft. 435 Tons- $36,500
- Orwig Road – 25 mm1- 275 ft. – 485 tons – $35,500
- Total – $204,500 – Budget based on a 20% increase from 2022 asphalt pricing